CONSTRUCTION PHOTOS of the
GREEN BUILDING / RENEWABLE ENERGY ADDITION
AT NAVARINO NATURE CENTER
Ground breaking at NNC on Monday, November 3, 2008 Zimmerman Aggregates excavating the lower level of the addition.

Pouring concrete footings -- Tuesday, November 4, 2008 Walls for lower level formed up, now pouring concrete into the INSULATED CONCRETE FORMS (ICF) Thursday, November 6, 2008
Digging the Geothermal trenches 12-2-2008 Laying the Geothermal lines in the trench. 12-3-2008
Walls go up on the Great Room -- 12-18-2008 Walls covered and window openings prepared. 12-23-2008
Putting the trusses in place -- 1-7-2009 Placing the sheathing on the roof. 1-8-2009
1-21-2009 Putting the roof on the Great Room 2-4-2009 Building wrapped, windows in, deck around south-side being built.
Drywall going up in the lobby -- Week of February 16 Plastering the walls in the Renewable Energy display room -- Week of February 24
Notice the Sun Tunnel skylights are in place. Geothermal Heat pump protected under tarp
Week of 3-2-2009 Lobby photos -- Plaster is finished, duct work going in place and start painting
South wall of Great Hall North wall of Great Hall
Interior heating element in Geothermal Heat Pump, blower is located underneath.
Exterior Views
South side and walk-way to deck. Solar panels will be installed later. North side of addition --
3 windows in the upper level, 2 lower windows in classroom area.
New entry in the lobby area. Week of 3-2-2009 Siding starts to go on the outside.
March 20, 2009 Volunteers finishing the paneling for the Great Room (This lumber was harvested from the site.)
March 25, 2009 Paneling on the walls, a beautiful sight.
Flooring goes down in the Great Room. Olsen's Rural Electric from Clintonville put the lights up in the Great Room.
Wet lab classroom completed, started moving items in. Recycled glass floor tiles go down on the lobby floor.
Energize LLC installs solar panels on the roof.
Navarino Nature Center - Green Building / Renewable Energy Education Addition -- 7-23-2009